Comment: 23. If it is affected, how long can I expect to be impacted? Response: How long a business could be affected by construction is relative to where the business […]
Comment: 2. The work planned for the interchanges with I-10 look to me to be of significant benefit in and of themselves. This should be Phase 1 of the project […]
Comment: 5. We should be informed of and deserve to know how DOTD projects work flow. Given my observations, road projects to step one, then 3 months later step 2, […]
Comment: 6. Is there an estimated construction start time and completion date? Very important to know to allay the fears of the tenants who might want to relocate at the […]
Comment: 3) Interstate Project Coordination Several I-10/I-110 projects are in the planning stage and should be coordinated and comprehensively analyzed to ensure the entire interstate system works effectively and efficiently. […]
Comment: 21. Why is Phase 2 financing being ramrodded almost ahead of a Phase 1 public review and comment> You don’t even know what the public wants, so how do […]
Comment: 35. How will out of state travelers be directed and diverted through the Baton Rouge area? Response: During construction, information, such as detour routes and when detours may be […]
Comment: 32. When will the detour routes be identified? Response: The traffic management plan will provide some detail on potential detour routes. When this plan is complete, it will be […]
Coleman Brown
Comment: 15. If my children are just now starting LSU, will it be finished before my children graduate? Response: We can not speculate the completion of construction versus your family’s […]