Updates

Coleman Brown

Comment:

7. Interstate 10 backs up to LA 415 Lobdell interchange every afternoon. How much further will it be backed up during construction?


Response:

The comment speaks to a future condition that cannot be accurately addressed, other than maintaining three lanes of traffic will be the most effective method of reducing congestion during construction. Lane closures should only be allowed during times when the queue analysis indicates the impacts would be acceptable, which will most likely be at night and on weekends.