Updates

Coleman Brown

Comment:

1. We don’t understand how long construction will take. Some reports say 5 years, some say 7. Where is the schedule?


Response:

The construction window for each individual segment of the project is projected at five to seven years. A construction schedule will be developed during detailed design under Stage 3, Final Design.